Shuttle Bus

Melrose Park Village June 2025 Project Update

20 June 2025

We’re thrilled to share the latest updates from site as we move closer to welcoming you home. There’s been plenty of action – here’s a quick snapshot:

  • The scaffolding is coming down! Buildings D, E and F are now fully revealed, and we’re 50% through removal on Buildings A and B. By late-June, all scaffolding will be down – offering a clearer view of what’s to come.
  • Green spaces taking shape. Landscaping works are underway on the rooftop garden and podium. Soil is currently being pumped in to support lush planting – with soil depths of up to 1.2m to accommodate future trees and landscaping features.
  • Basement works are complete. Services are in, and finishing touches like line marking, storage cages, and sealing will be wrapped up by the end of June.
  • In Buildings B and C, the last services works are underway where material hoists were previously located.
  • Endeavour Energy has energised the building’s new substation, and the temporary substation on Victoria Road will be removed
    late-June.
  • NBN Co is nearly done with fibre and in-apartment device installations.
  • Sekisui House internal quality inspections are in full swing across all buildings and will continue through July to ensure everything is just right.
  • Resident amenities are in progress, with fitout works underway and beginning to take shape.
  • Final survey is on the horizon. The last survey and measurements for the Strata Plan are scheduled for late June.

View our latest timelapse video below to see the transformation in action!

Trending news

M380 EXT LightRail 4K
31 Jan 2026

Stage 2 of Parramatta Light Rail Set to Power Ahead

Learn More
Aeris 5AUG CGGI DS LED Screen BINYAN FRO3385 S120 3Bed Living Final3500
10 Dec 2025

Parkview Appointed as Builder for Aeris at Melrose Park

Learn More
SEH005 Central Park V02A A watermark cropped
9 Dec 2025

More green spaces coming

Learn More