Melrose Park Village June Project Update

14 June 2023

With good weather over recent months, the project is progressing well as the construction team presses ahead with the early works.

Onsite, the final levels of basement excavation at the northern end of the site are almost complete. The structural piling works and capping beams are now complete on all sides.

In the months ahead the team will complete the underground carpark and then move on to laying the first slab. The crane will also be erected onsite.

The project is scheduled for completion in mid-2025.

If you have further questions in the meantime, please contact the Settlements Team at [email protected] or call us on 1300 MELROSE.

Trending news

M380 EXT LightRail 4K
31 Jan 2026

Stage 2 of Parramatta Light Rail Set to Power Ahead

Learn More
Aeris 5AUG CGGI DS LED Screen BINYAN FRO3385 S120 3Bed Living Final3500
10 Dec 2025

Parkview Appointed as Builder for Aeris at Melrose Park

Learn More
SEH005 Central Park V02A A watermark cropped
9 Dec 2025

More green spaces coming

Learn More