Shuttle Bus

Melrose Park Village June Project Update

14 June 2023

With good weather over recent months, the project is progressing well as the construction team presses ahead with the early works.

Onsite, the final levels of basement excavation at the northern end of the site are almost complete. The structural piling works and capping beams are now complete on all sides.

In the months ahead the team will complete the underground carpark and then move on to laying the first slab. The crane will also be erected onsite.

The project is scheduled for completion in mid-2025.

If you have further questions in the meantime, please contact the Settlements Team at [email protected] or call us on 1300 MELROSE.

Trending news

240529 SEKUSUI Day02 10 1955
30 June 2026

July School Holidays Ideas

Learn More
Untitled design (56)
25 June 2026

Melrose Central is Opening

Learn More
240529 SEKUSUI Day02 06 1118
23 June 2026

Second Free Shuttle Bus for Residents

Learn More