Willow Construction Update May 2026
20 May 2026
Construction Update Stage 3 Willow - May 2026
We are thrilled to share the latest news from Willow at Sanctuary. Our team has reached major milestones and we are one step closer to welcoming you to your new home. Here is a closer look at the incredible progress on site:
BUILDING H REACHES THE TOP
- Structure Complete: Building H has officially topped out.
- Formwork Removed: All concrete works are now complete, allowing our finishes trades to continue through to the remaining apartments.
- Walls Secured: External wall framing and weatherproofing are fully complete on the tower.
BEAUTIFUL EXTERIOR TOUCHES
- Windows Weatherproofed: Windows are fully installed and water-tested across all towers.
- Lobbies Protected: Level 1 lobby glass is installed and sealed against the elements.
- Stunning Facades: Elegant terracotta cladding is complete across the towers and podium.
- Townhouses Revealed: Brickwork on Levels 1 and 2 is cleaned, and scaffolding is down.
TRANSFORMING INTERIOR SPACES
- Buildings I & J Painted: Internal walls are fully sheeted, primed and beautifully painted.
- Building H Progress: Internal wall installation has climbed all the way to Level 28.
- Welcoming Lobbies: Building J and I lobbies are taking shape with fresh sheeting and paint.
- Grand Entrance: Groundwork has started on the Building H main lobby to prepare for walls.
COMMUNITY & OUTDOOR SPACES
- BBQ Pavilion: Painting has started on the Level 3 outdoor BBQ pavilion area.
- Architectural Columns: The unique external feature columns and soffits are now being painted.

Exciting times lay ahead for the Sanctuary community and Sekisui House Australia as we continue to create homes and communities that improve with time and last for generations.
If you have any questions, give us a call on 1300 726 288 to speak to our Customer Relations Representative.