Construction update - October 2019

01 October 2019


The structure for low rise building D has been completed whilst structures for low rise buildings B and C are nearing the halfway mark. Local residents can now see the golden construction screens clad across Tower A, which will allow the installation of the terracotta cladding as the building rises up floor by floor.

Internal wall-framing works have begun on the lower levels with each apartment beginning to take shape as rooms are laid out. Production has also begun on kitchens and internal joinery with the lower levels being installed first.


Current photos of the construction on the site.