Stage One - Landing, has reached many milestones in the last month and continues to progress well towards completion. See below some of the milestones reached:

  • Building A - progressing well with the jumpform at Level 7. Slabs have begun to be poured above the podium of Level 5
  • Building B & C - podium level is now on its final pours with the buildings soon to begin rising above the podium
  • Building D - Level 6 of the concrete slab has been poured and is now complete
  • Landscape Design in the Linear Park and podium level is now complete with trees and plants pre-ordered for the project.
     

Exciting times for the Wentworth Point Community and Sekisui House as we continue to create home and communities that improve with time and last for generations.

Current photos of the construction on the site.


 

Trending news

Light Rail image v4
31 Jan 2026

Stage 2 of Parramatta Light Rail Set to Power Ahead

Learn More
HERO CASE STUDY A 2
31 Aug 2025

Owner Occupiers drive $46.5mil launch success at Summit & Ridge

Learn More
Melrose Park 11
17 July 2025

Finding a home in Sanctuary - A Resident's Perspective

Learn More